Ram's Helps Motorists Through Spring RUSH

Apr 02, 2022 at 07:08 am by WGNS


(MURFREESBORO)  Spring and construction is ramping-up quickly. City Transportation Department's Deputy Director Ram Balachandran alerts motorists of potential traffic challenges from today through April 9, 2022. 

City Construction Projects

Old Pinnacle Building Demolition Work (N Maple St at W College St)

Expected No Lane Closures:  Monday through Friday:  Site construction work continues. Appropriate traffic controls and detours will be in place.

 

Oakland Court Development (Lokey Ave and Academy St)

Expected Road Closures:  Monday through Friday:  As part of the Oakland Court development, Academy St will be closed to through traffic between Palm Ct and Hembree St.  Lokey Ave will also be closed at Academy St.  Site construction work continues.  Appropriate traffic controls and detours will be in place.

 

Dr Martin Luther King Jr Sidewalk Improvement Project (SE Broad St and Middle Tennessee Blvd)

Expected Lane Closures:  Monday through Friday, 9:30 am to 3:00 pm:  Construction crews will be installing sidewalk and traffic signal improvements along the north side of MLK Blvd.  Westbound traffic between Middle Tennessee Blvd and SE Broad will be reduced from two lane to one lane.  Eastbound traffic will not be affected.  There will be right lane closures at MLK Blvd and Middle Tennessee Blvd.  Appropriate traffic controls will be in place.

 

Annual City Street Paving Projects

Expected Lane Closures:  Monday through Friday, 9:00 AM – 3:00 PM:  City contractor will be performing construction work at the following streets:

  1. Fortress Blvd and Franklin Rd (HC ramp and sidewalk work)
  2. Goldvalley Dr east of Rutherford Blvd (milling work)
  3. Bilbro St (casting adjustment work)

Expect lane shifts and traffic interruptions.  Appropriate traffic controls will be in place.

 

TDOT Resurfacing Projects

RUTHERFORD COUNTY, 266

The grading, drainage, construction of two concrete bulb tee beam bridges, signals, and paving on SR 266 (Jefferson Pike) from SR 102 (LM 5.0) to east of I-840 (LM 9).

Continuous 9 a.m. - 2:30 p.m. There will be flagging operations and short duration closures (5-10 min) for beam setting operations at bridge over Stones River. Gils Street will be closed at its intersection with SR 266 for utility line installations. A signed detour will be provided.

                                                                                                              

RUTHERFORD COUNTY I-24

Emergency In place paving

(Source: TDOT)

Tags: construction Murfreesboro news Ram Balachandran traffic reports WGNS
Sections: News